Keating Township Phase II Sewer Project

The Keating Township Supervisors wish to provide information on the Phase II Sanitary Sewer Project which is currently under construction. At the Keating Township Meeting held on September 22nd, 2014 the Supervisors accepted the lowest, qualified bids below.

Contract No. 1A – Wastewater Treatment Plant – Konzel Construction, Inc. (Erie, PA) - $2,725,000.

Contract No. 2A – Wastewater Collection System – C & R Directional Boring, LLC (Clearfield, PA) - $2,052,045.

Contract No. 3 – Grinder Pump Supply – Environmental One Corporation (Niskayuna, NY) - $788,065.

U.S. Department of Agriculture’s Rural Utilities Service (RUS) awarded a $4,827,000 grant and a $6,556,000 loan (2½% interest for a 38 year term) to finance Phase II and Phase III Wastewater Sewer Projects.

Phase II - Sewer Project Questions & Answers (updated as of 6/12/2015)

Phase II - Grinder Pump Owner’s Guide

Phase II - Grinder Pump Specification Sheets

Phase II - Powering a Grinder Pump with a Portable Generator

Phase II - How to Solvent Weld

Phase II - How to Install Electrical Lateral

 

Office of Open Records

Commonwealth Keystone Building
400 North Street, Plaza Level
Harrisburg, PA 17120-0225
Website: openrecords.state.pa.us
Email: openrecords@state.pa.us
Open Records Officer for Keating Township: Vickie Bickford

Township Meetings

The Keating Township Board of Supervisors meets at 6:00 pm on the first Wednesday of the month at the Township Building, unless otherwise advertised. The public is invited to attend.

Normal working hours are 7:00 am to 4:30 pm, except weekends and holidays.

Contact us

Keating Township
7160 Route 46
P.O. Box 103
East Smethport, PA 16730
Telephone: +1 814 887 9921

FAX: +1 814 887 9924
Email: keatingtwp@verizon.net